2 Walker Rd is a infrastructure proposed at 2 Walker Rd, Valhalla, NY 10595, USA in Mount Pleasant, NY. The project is currently pending before local land-use boards. Department of Water Supply G&E is listed as the developer on the public record. LocalForesight has tracked 2 public hearing appearances before Planning Board.

Project Overview

2 Walker Rd

The Department of Water Supply G&E is developing an infrastructure project at 2 Walker Road in Valhalla, Mount Pleasant. Beyond the address and project type, details regarding the scope of work, required approvals, and current status in the municipal review process are not available.

Subscriber content

Upgrade for full access to project intelligence.

Upgrade

Property Stats

Status Pending
Type Infrastructure
Address 2 Walker Rd, Valhalla, NY 10595, USA
Developer Department of Water Supply G&E

Map

Timeline

May 18, 2026
Planning Board
  • Approved 7-0 resolution for solar photovoltaic panel installation on roofs of UV treatment building and generator building
  • System uses rack and rail configuration with underground electric and equipment pad
  • Project at Department of Water Supply G&E facility, OB-2 Zone
  • Board consultant drafted resolution; board had previously reviewed project

Next steps

  • None; resolution approved and adopted
May 7, 2026
Planning Board
  • Approved for resolution preparation — Board directed preparation of approval resolution (5-0 vote)
  • Project: Rooftop solar installation on two buildings at 2 Walker Road (Department of Water Supply facility)
  • UV Treatment Building: 601 kW solar array; Four Bay Building: 177 kW solar array
  • Building heights confirmed: UV Building 30.1 ft, Four Bay Building 38.8 ft; solar panels add 6–8 inches, bringing max height to 39.9 ft
  • Underground utility connections to equipment pad with seven-foot chain link fence; no conditions imposed

Next steps

  • Approval resolution to be voted on at next Planning Board meeting
  • No additional submissions or conditions required

Subscriber content

Upgrade for full access to project intelligence.

Upgrade

Sentiment

9 /10

From Planning Board · May 18, 2026

  • Board unanimously supportive with all seven members voting aye
  • No public opposition or concerns raised during discussion
  • Matter presented as routine approval following prior review and consultant-drafted resolution