151 Fenimore Rd

Sign in to follow

151 Fenimore Rd is a commercial proposed at 151 Fenimore Rd, Mamaroneck, NY, 10543-3538 in Mamaroneck (Village), NY. The project is currently pending before local land-use boards. New York SMSA Limited Partnership, DBA Verizon Wireless is listed as the developer on the public record. LocalForesight has tracked 1 public hearing appearance before Planning Board.

Project Overview

151 Fenimore Rd

New York SMSA Limited Partnership, doing business as Verizon Wireless, is developing a commercial project at 151 Fenimore Road in the Village of Mamaroneck. The project involves wireless telecommunications infrastructure. No additional details about the proposed scope, zoning classification, variances sought, or approval status are available in the project record.

Subscriber content

Upgrade for full access to project intelligence.

Upgrade

Property Stats

Status Pending
Type Commercial
Address 151 Fenimore Rd, Mamaroneck, NY, 10543-3538
Developer New York SMSA Limited Partnership, DBA Verizon Wireless

Map

Timeline

Jun 15, 2026
Planning Board
  • Deferred to July 8 public hearing for additional submissions and FCC compliance documentation
  • Applicant to submit: updated RF/FCC compliance report, waiver request review, and draft resolution by June 24
  • Aesthetics condition added: all new/replacement antennas must match existing color on roof; no additional lighting
  • Recognized as eligible facilities request under federal law (Section 6409); 60-day approval timeline triggered upon deemed complete application
  • Application not deemed complete tonight; waiver request received and under board review

Next steps

  • Updated RF/FCC compliance report due by June 24 deadline
  • Public hearing and board review scheduled for July 8 meeting with draft resolution prepared
  • Board has 60 days from deemed complete application date to approve (no August meetings; safety meeting after July 8)

Subscriber content

Upgrade for full access to project intelligence.

Upgrade

Sentiment

7 /10

From Planning Board · Jun 15, 2026

  • Board supportive of project efficiency; Chair and members acknowledged federal preemption and expedited timeline
  • Board member Richard raised electromagnetic/RF wave safety concerns from neighbors; sought current FCC compliance proof rather than outdated documentation
  • Applicant cooperative on conditions and documentation; no public opposition recorded in transcript