Board Eases Sewer Fix Deadline for Equinox Gym
Eastchester's Planning Board approved an Equinox gym and other new tenants for 750 White Plains Road, agreeing to allow required sewer mitigation work to proceed concurrently with construction rather than delaying building permits. This decision balances the town's need to protect its sensitive sewer infrastructure with the developer's warning that strict upfront demands could jeopardize a major new commercial project.
What Happened
- The original 2021 approval for 750 White Plains Road required sewer mitigation once total flow exceeded 21,500 gallons per day; the proposed five new tenants now trigger this threshold, leading to the current debate.
- Town staff initially recommended requiring Equinox's sewer mitigation be completed before its building permit, citing the sensitive sewer shed and the gym's substantial contribution to flow.
- The applicant argued this upfront requirement would cause indefinite delays due to county health department approvals and mitigation design, potentially forcing them to lose Equinox as a tenant.
- Board members and the town's consultant acknowledged the developer's concerns, noting that Equinox's estimated 18-month build-out provides ample time for sewer mitigation to occur in parallel with construction.
- The town's consulting engineer proposed analyzing the Leawood Road sewer system, which is in better condition than Harney Road, to determine its capacity for the additional flow and pinpoint effective mitigation measures.
Project Outcomes
- LT Eastchester (750 White Plains Road): Site plan and exterior renovations approved, enabling the conversion of the former department store into a multi-tenant building.
- Equinox (750 White Plains Road): Special permit approved for the gym, with the board agreeing to allow sewer mitigation to proceed concurrently with construction rather than delaying building permits.
- Cava Restaurant (750 White Plains Road): Special permit approved for the restaurant, contingent on the overall project's sewer mitigation being completed before occupancy.
- Tate Bakery (750 White Plains Road): Special permit approved for the bakery, contingent on the overall project's sewer mitigation being completed before occupancy.
What's Next
- The town's consulting engineer, highway department, and applicant's engineer will meet to analyze the Leawood Road sewer system and pinpoint specific mitigation requirements.
- The developer must coordinate with county and town officials to design, approve, and implement the agreed-upon sewer mitigation measures concurrently with the 18-month Equinox build-out period.